The realisation tracker

From announcement to productionஒப்பந்தங்கள்

Every commitment moves through five stages: announced → land → clearance → commissioning → jobs. We record the date of each, the evidence for each, and we publish the ones that stopped.

Announced (tracked)

₹1.55 lakh crore

as at 31 Jul 2026 · source: Guidance releases; filings

Traced to a signed, funded commitment

₹38,900 crore

as at 31 Jul 2026 · source: Arivu realisation tracker

Realised

25%

as at 31 Jul 2026 · source: Arivu arithmetic

The five-stage chain

1 · Announced

₹1.55 lakh crore
14 · 100%

2 · Land

₹1.43 lakh crore
12 · 92%

3 · Clearance

₹67,400 crore
10 · 43%

4 · Commissioning

₹56,800 crore
8 · 37%

5 · Jobs

₹28,000 crore
5 · 18%

Value shown is announced ₹, narrowing as commitments progress. The announced-to-deployed discount is 60–80% C and is applied to every headline figure on this platform.

Every commitment, every stage

5 realised · 6 in pipeline · 3 lapsed

RefCounterpartyClusterAnnouncedTracedStageStatus
MOU-2023-041Hosur EV SystemsPhase I commissioned; second line under fit-out.Hosur₹12,500 crore₹7,400 croreBrealised
MOU-2022-118Oragadam DrivetrainOragadam₹8,600 crore₹6,100 croreBrealised
MOU-2024-007Vandalur Electronics AssemblySriperumbudur₹21,000 crore₹9,800 croreCpipeline
MOU-2023-232Tuticorin Speciality ChemicalsThoothukudi₹6,400 crore₹2,600 croreCpipeline
MOU-2024-055Kayalpatnam Green HydrogenAnnounced at investors' meet; land identified, CRZ clearance pending.Thoothukudi₹74,000 crore₹3,100 croreCpipeline
MOU-2022-090Palladam Garment ExportsTiruppur₹2,100 crore₹1,500 croreBrealised
MOU-2023-160Suramangalam StainlessNo land allotment traced 24 months after announcement. No public explanation found.Salem₹9,200 croreClapsed
MOU-2024-021Perungudi Capability CentreChennai IT corridor₹3,400 crore₹2,900 croreBrealised
MOU-2023-199Arani Display ModulesSriperumbudur₹5,600 crore₹2,200 croreCpipeline
MOU-2021-072Harbour Edge LogisticsLand allotted; project not commissioned. Counterparty cited demand shortfall in filings.Thoothukudi₹1,800 croreClapsed
MOU-2024-088Nilgiri Battery WorksHosur₹4,200 crore₹1,300 croreCpipeline
MOU-2022-145Peelamedu PumpsCoimbatore₹1,400 crore₹1,100 croreBrealised
MOU-2023-118Singaperumal CastingsCounterparty amalgamated before commissioning; commitment not carried forward.Oragadam₹2,600 croreClapsed
MOU-2024-133Thoraipakkam Engineering R&DChennai IT corridor₹2,200 crore₹900 croreCpipeline

The lapsed tab carries the reason where one is on the record, and “no public explanation found” where it is not — which is itself a finding, and a more useful one than silence.

The announced-to-deployed discount

A headline investment figure for any Indian state should be read at 20–40% of face value. The discount is 60–80% C, applied to every headline figure on this platform and stated wherever it is used. A tracker that only shows what is progressing is a promotion tool — the lapsed tab is what makes the other three credible, and it is the tab no government portal will ever build.